PROGRESS CIVIL - ORF SEMARANG |
No |
Deskripsi |
Volume |
Unit |
Sebelumnya [20 Agustus 2023] |
Terbaru [27 August 2023] |
Progress |
% |
Progress |
% |
1 | Pemancangan | 235 | Titik | 235 | 100% | 235 | 100% |
2 | Pilecutting | 235 | Titik | 235 | 100% | 235 | 100% |
3 | Pembobokan | 234 | Titik | 235 | 100% | 234 | 100% |
4 | Fabrikasi Rebar PHT | 5785.7 | Kg | 5785.7 | 100% | 5785.7 | 100% |
5 | Pemasangan Bekisting PHT | 29.61 | M2 | 29.61 | 100% | 29.61 | 100% |
6 | Instalasi Rebar PHT | 5785.7 | Kg | 5785.7 | 100% | 5785.7 | 100% |
7 | Pengecoran PHT | 35.49 | M3 | 35.49 | 100% | 35.49 | 100% |
8 | Fabrikasi Rebar Pilecap | 65247.3 | Kg | 65247.3 | 100% | 65247.3 | 100% |
9 | Instalasi Rebar Pilecap | 65247.3 | Kg | 65247.3 | 100% | 65247.3 | 100% |
10 | Pemasangan Bekisting Pilecap | 1709.52 | M2 | 1707.22 | 100% | 1709.52 | 100% |
11 | Pengecoran Pilecap | 393.52 | M3 | 393.52 | 100% | 393.52 | 100% |
12 | Fabrikasi Rebar Beam | 118979 | Kg | 118764 | 100% | 118979 | 100% |
13 | Instalasi Rebar Beam | 118979 | Kg | 118764 | 100% | 118979 | 100% |
14 | Pengecoran Beam | 535.26 | M3 | 535.26 | 100% | 535.26 | 100% |
15 | Pemasangan Bekisting Beam | 2215.95 | M2 | 2215.95 | 100% | 2215.95 | 100% |
16 | Fabrikasi Rebar Slab | 208655 | Kg | 208655 | 100% | 208655 | 100% |
17 | Pemasangan Bekisting Slab | 6179.25 | M2 | 6179.25 | 100% | 6179.25 | 100% |
18 | Instalasi Rebar Slab | 212233 | Kg | 212233 | 100% | 212233 | 100% |
19 | Pengecoran Slab | 1982.24 | M3 | 1982.24 | 100% | 1982.24 | 100% |
PROGRESS CIVIL - ORF BATANG |
No |
Deskripsi |
Volume |
Unit |
Sebelumnya [07 June 2023] |
Terbaru [27 August 2023] |
Progress |
% |
Progress |
% |
1 | Preparation Work |
| Site Preparation | 1 | Ls | 1 | 100% | 1 | 100% |
| Land Clearing | 1 | Ls | 1 | 100% | 1 | 100% |
| Access Road | 1 | Ls | 1 | 100% | 1 | 100% |
| Site Facility | 1 | Ls | 1 | 100% | 1 | 100% |
2 | Pekerjaan Pagar |
| Penggalian Pondasi Pagar | 257 | m | 257 | 100% | 257 | 100% |
| Pondasi Foot Plate | | | | | | |
| Lean Concrete | 85 | Ea | 85 | 100% | 85 | 100% |
| Fabrikasi | 85 | Ea | 85 | 100% | 85 | 100% |
| Instalasi | 85 | Ea | 85 | 100% | 85 | 100% |
| Pengecorann | 85 | Ea | 85 | 100% | 85 | 100% |
| Pondasi Batu Kali | 257 | m | 257 | 100% | 257 | 100% |
| Instalasi Pagar | 257 | m | 165.25 | 64% | 257 | 100% |
| Instalasi Gerbang | 1 | Ls | 0 | 0% | 1 | 100% |
3 | Pekerjaan Pondasi Equipment dan Pedestal |
| Pig Reciever | | | | | | |
| Penggalian | 2 | ea | 2 | 100% | 2 | 100% |
| Pondasi Foot Plate | | | | | | |
| Lean Concrete | 2 | ea | 2 | 100% | 2 | 100% |
| Pasir Urug | 2 | ea | 2 | 100% | 2 | 100% |
| Fabrikasi | 2 | ea | 2 | 100% | 2 | 100% |
| Instalasi | 2 | ea | 2 | 100% | 2 | 100% |
| Pengecoran | 2 | ea | 2 | 100% | 2 | 100% |
| Nitrogen Shelter | | | | | | |
| Penggalian | 2 | ea | 2 | 100% | 2 | 100% |
| Pondasi Foot Plate | | | | | | |
| Lean Concrete | 2 | ea | 0 | 0% | 2 | 100% |
| Pasir Urug | 2 | ea | 0 | 0% | 2 | 100% |
| Fabrikasi | 2 | ea | 0 | 0% | 2 | 100% |
| Instalasi | 2 | ea | 0 | 0% | 2 | 100% |
| Pengecoran | 2 | ea | 0 | 0% | 2 | 100% |
| Instrument Shelter | | | | | | |
| Penggalian | 4 | ea | 4 | 100% | 4 | 100% |
| Pondasi Foot Plate | | | | | | |
| Lean Concrete | 4 | ea | 0 | 0% | 4 | 100% |
| Pasir Urug | 4 | ea | 0 | 0% | 4 | 100% |
| Fabrikasi | 4 | ea | 0 | 0% | 4 | 100% |
| Instalasi | 4 | ea | 0 | 0% | 4 | 100% |
| Pengecoran | 4 | ea | 0 | 0% | 4 | 100% |
| Pedestal | | | | | | |
| Penggalian | 27 | ea | 0 | 0% | 27 | 100% |
| Pondasi Foot Plate | | | | | | |
| Lean Concrete | 27 | ea | 0 | 0% | 27 | 100% |
| Pasir Urug | 27 | ea | 0 | 0% | 27 | 100% |
| Fabrikasi | 27 | ea | 5 | 19% | 27 | 100% |
| Instalasi | 27 | ea | 0 | 0% | 27 | 100% |
| Pengecoran | 27 | ea | 0 | 0% | 27 | 100% |
4 | Pekerjaan Drainase |
| Penggalian | 322.183 | m | 30.741 | 10% | 322.183 | 100% |
| Pekerjaan U Ditch | | | | | | |
| Urugan Pasir | 322.183 | m | 297.786 | 92% | 322.183 | 100% |
| Fabrikasi | 322.183 | m | 0 | 0% | 322.183 | 100% |
| Instalasi | 322.183 | m | 272.56 | 85% | 322.183 | 100% |
5 | Pekerjaan Jalan |
| Penggalian Jalan | 58.499 | m | 58.499 | 100% | 58.499 | 100% |
| Penghamparan dan Pemadatan | 58.499 | m | 58.499 | 100% | 58.499 | 100% |
| Penghamparan Subbase | 58.499 | m | 58.499 | 100% | 58.499 | 100% |
| Pemasangan Wiremesh dan | 58.499 | m | 46.499 | 79% | 58.499 | 100% |
| Pengecoran Jalan | 58.499 | m | 46.499 | 79% | 58.499 | 100% |
6 | Pekerjaan Steel Structure |
| Nitrogen Shelter | 1 | LS | 0 | 0% | 1 | 100% |
| Instrument Shelter | 1 | LS | 0 | 0% | 1 | 100% |