Progress Civil

Progress Civil

CUT OFF : 27 August 2023
PROGRESS CIVIL - ORF SEMARANG
No Deskripsi Volume Unit Sebelumnya [20 Agustus 2023] Terbaru [27 August 2023]
Progress % Progress %
1Pemancangan235Titik235100%235100%
2Pilecutting235Titik235100%235100%
3Pembobokan234Titik235100%234100%
4Fabrikasi Rebar PHT5785.7Kg5785.7100%5785.7100%
5Pemasangan Bekisting PHT29.61M229.61100%29.61100%
6Instalasi Rebar PHT5785.7Kg5785.7100%5785.7100%
7Pengecoran PHT35.49M335.49100%35.49100%
8Fabrikasi Rebar Pilecap65247.3Kg65247.3100%65247.3100%
9Instalasi Rebar Pilecap65247.3Kg65247.3100%65247.3100%
10Pemasangan Bekisting Pilecap1709.52M21707.22100%1709.52100%
11Pengecoran Pilecap393.52M3393.52100%393.52100%
12Fabrikasi Rebar Beam118979Kg118764100%118979100%
13Instalasi Rebar Beam118979Kg118764100%118979100%
14Pengecoran Beam535.26M3535.26100%535.26100%
15Pemasangan Bekisting Beam2215.95M22215.95100%2215.95100%
16Fabrikasi Rebar Slab208655Kg208655100%208655100%
17Pemasangan Bekisting Slab6179.25M26179.25100%6179.25100%
18Instalasi Rebar Slab212233Kg212233100%212233100%
19Pengecoran Slab1982.24M31982.24100%1982.24100%
PROGRESS CIVIL - ORF BATANG
No Deskripsi Volume Unit Sebelumnya [07 June 2023] Terbaru [27 August 2023]
Progress % Progress %
1Preparation Work
Site Preparation1Ls1100%1100%
Land Clearing1Ls1100%1100%
Access Road1Ls1100%1100%
Site Facility1Ls1100%1100%
2Pekerjaan Pagar
Penggalian Pondasi Pagar257m257100%257100%
Pondasi Foot Plate
Lean Concrete85Ea85100%85100%
Fabrikasi85Ea85100%85100%
Instalasi85Ea85100%85100%
Pengecorann85Ea85100%85100%
Pondasi Batu Kali257m257100%257100%
Instalasi Pagar257m165.2564%257100%
Instalasi Gerbang1Ls00%1100%
3Pekerjaan Pondasi Equipment dan Pedestal
Pig Reciever
Penggalian2ea2100%2100%
Pondasi Foot Plate
Lean Concrete2ea2100%2100%
Pasir Urug2ea2100%2100%
Fabrikasi2ea2100%2100%
Instalasi2ea2100%2100%
Pengecoran2ea2100%2100%
Nitrogen Shelter
Penggalian2ea2100%2100%
Pondasi Foot Plate
Lean Concrete2ea00%2100%
Pasir Urug2ea00%2100%
Fabrikasi2ea00%2100%
Instalasi2ea00%2100%
Pengecoran2ea00%2100%
Instrument Shelter
Penggalian4ea4100%4100%
Pondasi Foot Plate
Lean Concrete4ea00%4100%
Pasir Urug4ea00%4100%
Fabrikasi4ea00%4100%
Instalasi4ea00%4100%
Pengecoran4ea00%4100%
Pedestal
Penggalian27ea00%27100%
Pondasi Foot Plate
Lean Concrete27ea00%27100%
Pasir Urug27ea00%27100%
Fabrikasi27ea519%27100%
Instalasi27ea00%27100%
Pengecoran27ea00%27100%
4Pekerjaan Drainase
Penggalian322.183m30.74110%322.183100%
Pekerjaan U Ditch
Urugan Pasir322.183m297.78692%322.183100%
Fabrikasi322.183m00%322.183100%
Instalasi322.183m272.5685%322.183100%
5Pekerjaan Jalan
Penggalian Jalan58.499m58.499100%58.499100%
Penghamparan dan Pemadatan58.499m58.499100%58.499100%
Penghamparan Subbase58.499m58.499100%58.499100%
Pemasangan Wiremesh dan58.499m46.49979%58.499100%
Pengecoran Jalan58.499m46.49979%58.499100%
6Pekerjaan Steel Structure
Nitrogen Shelter1LS00%1100%
Instrument Shelter1LS00%1100%