1.1 | Milestone Project | 100% | Done | 2023-04-17 | 2023-11-30 | 2023-10-01 | 74 days | | |
1.1.1 | Surat Perintah VO Offtake Station Batang | 100% | Done | 2023-04-17 | 2023-04-17 | 2023-10-01 | - | | |
1.1.2 | Perancangan Selesai | 100% | Done | 2023-06-15 | 2023-06-15 | 2023-10-01 | - | | |
1.1.3 | Pengadaan LLI Selesai | 100% | Done | 2023-10-16 | 2023-10-16 | 2023-10-01 | - | | |
1.1.4 | Mechanical Completion | 100% | Done | 2023-11-24 | 2023-11-24 | 2023-10-01 | - | | |
1.1.5 | Privisonal Hand Over | 100% | Done | 2023-11-30 | 2023-11-30 | 2023-10-01 | - | | |
1.2 | Pekerjaan Persiapan | 0% | Not Yet | 2023-04-18 | 2023-05-23 | | 265 days | | |
1.2.1 | Project Facilities | 0% | Not Yet | 2023-04-18 | 2023-05-15 | | 273 days | | |
1.2.2 | Survey & Investigation | 0% | Not Yet | 2023-04-26 | 2023-05-23 | | 265 days | | |
1.3 | Engineering | 100% | Done | 2023-05-05 | 2023-06-15 | 2023-10-01 | 242 days | | |
1.3.1 | Basic Engineering Design | 100% | Done | 2023-05-05 | 2023-06-02 | 2023-10-01 | - | | |
1.3.2 | Detailed Engineering Design | 100% | Done | 2023-05-16 | 2023-06-15 | 2023-10-01 | - | | |
1.4 | Procurement | 5% | On Prog | 2023-05-25 | 2023-11-07 | | 97 days | | |
1.4.1 | Pengadaan Bahan | 5% | On Prog | 2023-05-25 | 2023-11-07 | | 97 days | | |
1.4.1.1 | Long Lead Items | 40% | On Prog | 2023-05-25 | 2023-10-16 | | 119 days | | |
1.4.1.1.1 | Shut Down Valve | 60% | On Prog | 2023-05-25 | 2023-10-16 | | 119 days | | |
1.4.1.1.2 | Slam Shut Valve | 70% | On Prog | 2023-05-25 | 2023-10-16 | | 119 days | | |
1.4.1.1.3 | Pressure Safety Valve | 70% | On Prog | 2023-05-25 | 2023-10-16 | | 119 days | | |
1.4.1.1.4 | Metering & Regulating System | 0% | Not Yet | 2023-05-25 | 2023-10-16 | | 119 days | | |
1.4.1.1.5 | Monolithic Insulation Joint | 0% | Not Yet | 2023-05-25 | 2023-07-06 | | 221 days | | |
1.4.1.2 | Process Safety | 0% | Not Yet | 2023-06-05 | 2023-11-07 | | 97 days | | |
1.4.1.2.1 | Fire Extinguisher | 0% | Not Yet | 2023-06-05 | 2023-07-12 | | 215 days | | |
1.4.1.2.2 | Fire Suppression System | 0% | Not Yet | 2023-06-14 | 2023-10-09 | | 126 days | | |
1.4.1.2.3 | F & G System | 0% | Not Yet | 2023-06-14 | 2023-10-09 | | 126 days | | |
1.4.1.2.4 | Safety Sign | 0% | Not Yet | 2023-07-13 | 2023-11-07 | | 97 days | | |
1.4.1.3 | Mechanical | 0% | Not Yet | 2023-06-12 | 2023-10-06 | | 129 days | | |
1.4.1.3.1 | Liquid Drum | 0% | Not Yet | 2023-06-12 | 2023-07-24 | | 203 days | | |
1.4.1.3.2 | Slug Catcher | 0% | Not Yet | 2023-06-12 | 2023-09-01 | | 164 days | | |
1.4.1.3.3 | Odorizer System | 0% | Not Yet | 2023-06-12 | 2023-10-06 | | 129 days | | |
1.4.1.3.4 | Utility Water Tank | 0% | Not Yet | 2023-06-12 | 2023-08-04 | | 192 days | | |
1.4.1.4 | Electrical | 0% | Not Yet | 2023-06-12 | 2023-10-05 | | 130 days | | |
1.4.1.4.1 | LV Distribution Panel | 0% | Not Yet | 2023-06-12 | 2023-09-29 | | 136 days | | |
1.4.1.4.2 | UPS & DC System | 0% | Not Yet | 2023-06-12 | 2023-10-05 | | 130 days | | |
1.4.1.4.3 | Lighting & Receptacle System | 0% | Not Yet | 2023-06-12 | 2023-10-02 | | 133 days | | |
1.4.1.4.4 | Grounding & Lightning System | 0% | Not Yet | 2023-06-12 | 2023-10-05 | | 130 days | | |
1.4.1.4.5 | CCTV System | 0% | Not Yet | 2023-06-12 | 2023-09-15 | | 150 days | | |
1.4.1.4.6 | Power Cables | 0% | Not Yet | 2023-06-12 | 2023-08-14 | | 182 days | | |
1.4.1.4.7 | Cable Tray | 0% | Not Yet | 2023-06-12 | 2023-07-31 | | 196 days | | |
1.4.1.4.8 | Bulk Materials | 0% | Not Yet | 2023-06-12 | 2023-07-31 | | 196 days | | |
1.4.1.5 | Instrumentation | 0% | Not Yet | 2023-06-12 | 2023-10-06 | | 129 days | | |
1.4.1.5.1 | Actuated Valve | 0% | Not Yet | 2023-06-12 | 2023-09-15 | | 150 days | | |
1.4.1.5.2 | PCS/RTU System | 0% | Not Yet | 2023-06-12 | 2023-10-06 | | 129 days | | |
1.4.1.5.3 | Instrument Cables | 0% | Not Yet | 2023-06-12 | 2023-08-14 | | 182 days | | |
1.4.1.5.4 | Cable Tray | 0% | Not Yet | 2023-06-12 | 2023-07-31 | | 196 days | | |
1.4.1.5.5 | Instrument Fittings | 0% | Not Yet | 2023-06-12 | 2023-07-31 | | 196 days | | |
1.4.1.5.6 | Field Instrument | 0% | Not Yet | 2023-06-12 | 2023-09-15 | | 150 days | | |
1.4.1.5.7 | Junction Box | 0% | Not Yet | 2023-06-12 | 2023-09-08 | | 157 days | | |
1.4.1.5.8 | Bulk Materials | 0% | Not Yet | 2023-06-12 | 2023-09-08 | | 157 days | | |
1.4.1.6 | Pipeline | 0% | Not Yet | 2023-06-12 | 2023-10-17 | | 118 days | | |
1.4.1.6.1 | Barred Tee | 0% | Not Yet | 2023-06-12 | 2023-10-17 | | 118 days | | |
1.4.1.6.2 | Pipeline Material | 0% | Not Yet | 2023-06-12 | 2023-10-17 | | 118 days | | |
1.4.1.6.3 | Manual Valve | 0% | Not Yet | 2023-06-12 | 2023-10-17 | | 118 days | | |
1.4.1.6.4 | Bulk Materials | 0% | Not Yet | 2023-06-12 | 2023-10-17 | | 118 days | | |
1.4.1.7 | Piping | 0% | Not Yet | 2023-06-12 | 2023-08-25 | | 171 days | | |
1.4.1.7.1 | Pipe Material | 0% | Not Yet | 2023-06-12 | 2023-08-11 | | 185 days | | |
1.4.1.7.2 | Specialty Items | 0% | Not Yet | 2023-06-12 | 2023-08-25 | | 171 days | | |
1.4.1.7.3 | Manual Valve | 0% | Not Yet | 2023-06-12 | 2023-08-25 | | 171 days | | |
1.4.1.7.4 | Bulk Material (Bot&nuts, Garket, Flange, Elbow, etc) | 0% | Not Yet | 2023-06-12 | 2023-08-04 | | 192 days | | |
1.4.1.8 | Civil | 0% | Not Yet | 2023-06-05 | 2023-10-11 | | 124 days | | |
1.4.1.8.1 | Beton | 0% | Not Yet | 2023-06-14 | 2023-07-03 | | 224 days | | |
1.4.1.8.2 | Besi Beton | 0% | Not Yet | 2023-06-05 | 2023-06-22 | | 235 days | | |
1.4.1.8.3 | Steel Structure | 0% | Not Yet | 2023-06-20 | 2023-08-08 | | 188 days | | |
1.4.1.8.4 | HVAC System | 0% | Not Yet | 2023-06-22 | 2023-09-19 | | 146 days | | |
1.4.1.8.5 | Miscellenous Items | 0% | Not Yet | 2023-07-04 | 2023-10-11 | | 124 days | | |
1.5 | Construction | 5% | On Prog | 2023-05-29 | 2023-11-24 | | 80 days | | |
1.5.1 | Site Preparation | 50% | On Prog | 2023-05-29 | 2023-06-13 | | 244 days | | |
1.5.1.1 | Pekerjaan Cut & Fill | 50% | On Prog | 2023-05-29 | 2023-05-31 | | 257 days | | |
1.5.1.2 | Pekerjaan Pemadatan Tanah | 100% | Done | 2023-06-01 | 2023-06-07 | 2023-10-01 | - | | |
1.5.1.3 | Pekerjaan Sand Cone Test | 0% | Not Yet | 2023-06-08 | 2023-06-13 | | 244 days | | |
1.5.2 | Pembangunan Control Building (inc. Water Tank) | 0% | Not Yet | 2023-06-14 | 2023-11-24 | | 80 days | | |
1.5.2.1 | Pekerjaan Persiapan | 0% | Not Yet | 2023-06-14 | 2023-06-22 | | 235 days | | |
1.5.2.2 | Pekerjaan Pembesian Pondasi | 0% | Not Yet | 2023-06-23 | 2023-07-03 | | 224 days | | |
1.5.2.3 | Pekerjaan Pengecoran Beton | 0% | Not Yet | 2023-07-04 | 2023-07-10 | | 217 days | | |
1.5.2.4 | Pekerjaan Struktur Atas | 0% | Not Yet | 2023-07-11 | 2023-08-08 | | 188 days | | |
1.5.2.5 | Pekerjaan Atap Bangunan | 0% | Not Yet | 2023-08-09 | 2023-08-28 | | 168 days | | |
1.5.2.6 | Pemasangan Fasilitas Bangunan Lainnya | 0% | Not Yet | 2023-08-29 | 2023-09-11 | | 154 days | | |
1.5.2.7 | Pemasangan PCS System | 0% | Not Yet | 2023-10-09 | 2023-10-13 | | 122 days | | |
1.5.2.8 | Pemasangan UPS System | 0% | Not Yet | 2023-10-06 | 2023-10-12 | | 123 days | | |
1.5.2.9 | Pemasangan HVAC System | 0% | Not Yet | 2023-10-13 | 2023-10-26 | | 109 days | | |
1.5.2.10 | Pemasangan Fire & Gas Detector | 0% | Not Yet | 2023-10-27 | 2023-11-07 | | 97 days | | |
1.5.2.11 | Pemasangan Fire Suppression System | 0% | Not Yet | 2023-11-03 | 2023-11-15 | | 89 days | | |
1.5.2.12 | Pemasangan Lighting & Receptacle | 0% | Not Yet | 2023-10-03 | 2023-10-18 | | 117 days | | |
1.5.2.13 | Pemasangan Lightning Protection | 0% | Not Yet | 2023-10-19 | 2023-10-31 | | 104 days | | |
1.5.2.14 | Pemasangan LV Panel | 0% | Not Yet | 2023-10-02 | 2023-10-06 | | 129 days | | |
1.5.2.15 | Precommissioning Control Building | 0% | Not Yet | 2023-11-16 | 2023-11-24 | | 80 days | | |
1.5.3 | Pemasangan Odorizer System | 0% | Not Yet | 2023-06-14 | 2023-10-20 | | 115 days | | |
1.5.3.1 | Pekerjaan Persiapan | 0% | Not Yet | 2023-06-14 | 2023-06-22 | | 235 days | | |
1.5.3.2 | Pekerjaan Pembesian Pondasi | 0% | Not Yet | 2023-06-23 | 2023-06-28 | | 229 days | | |
1.5.3.3 | Pekerjaan Pengecoran Beton | 0% | Not Yet | 2023-07-04 | 2023-07-06 | | 221 days | | |
1.5.3.4 | Pekerjaan Pemasangan Shelter | 0% | Not Yet | 2023-08-09 | 2023-08-15 | | 181 days | | |
1.5.3.5 | Pekerjaan Pemasangan Odorizer System | 0% | Not Yet | 2023-10-09 | 2023-10-13 | | 122 days | | |
1.5.3.6 | Interconnecting to Other System | 0% | Not Yet | 2023-10-16 | 2023-10-17 | | 118 days | | |
1.5.3.7 | Precommissioning Odorizer System | 0% | Not Yet | 2023-10-18 | 2023-10-20 | | 115 days | | |
1.5.4 | Pemasangan Metering & Regulating Station | 0% | Not Yet | 2023-06-14 | 2023-11-10 | | 94 days | | |
1.5.4.1 | Pekerjaan Persiapan | 0% | Not Yet | 2023-06-14 | 2023-06-22 | | 235 days | | |
1.5.4.2 | Pekerjaan Pembesian Pondasi | 0% | Not Yet | 2023-06-23 | 2023-06-28 | | 229 days | | |
1.5.4.3 | Pekerjaan Pengecoran Beton | 0% | Not Yet | 2023-07-04 | 2023-07-06 | | 221 days | | |
1.5.4.4 | Pekerjaan Pemasangan Shelter | 0% | Not Yet | 2023-08-16 | 2023-08-28 | | 168 days | | |
1.5.4.5 | Pekerjaan Pemasangan Metering & Regulating Station | 0% | Not Yet | 2023-10-17 | 2023-10-25 | | 110 days | | |
1.5.4.6 | Pemasangan Lighting System | 0% | Not Yet | 2023-10-03 | 2023-10-16 | | 119 days | | |
1.5.4.7 | Pemasangan Fire Detection System | 0% | Not Yet | 2023-10-17 | 2023-10-25 | | 110 days | | |
1.5.4.8 | Pemasangan CCTV | 0% | Not Yet | 2023-10-26 | 2023-11-03 | | 101 days | | |
1.5.4.9 | Interconnecting to Other System | 0% | Not Yet | 2023-11-06 | 2023-11-07 | | 97 days | | |
1.5.4.10 | Precommissioning Odorizer System | 0% | Not Yet | 2023-11-08 | 2023-11-10 | | 94 days | | |
1.5.5 | Pemasangan Sludge Catcher | 0% | Not Yet | 2023-06-14 | 2023-09-14 | | 151 days | | |
1.5.5.1 | Pekerjaan Persiapan | 0% | Not Yet | 2023-06-14 | 2023-06-16 | | 241 days | | |
1.5.5.2 | Pekerjaan Pembesian Pondasi | 0% | Not Yet | 2023-06-23 | 2023-06-28 | | 229 days | | |
1.5.5.3 | Pekerjaan Pengecoran Beton | 0% | Not Yet | 2023-07-04 | 2023-07-06 | | 221 days | | |
1.5.5.4 | Pekerjaan Pemasangan Sludge Catcher | 0% | Not Yet | 2023-09-04 | 2023-09-07 | | 158 days | | |
1.5.5.5 | Interconnecting to Other System | 0% | Not Yet | 2023-09-08 | 2023-09-11 | | 154 days | | |
1.5.5.6 | Precommissioning Sludge Catcher | 0% | Not Yet | 2023-09-12 | 2023-09-14 | | 151 days | | |
1.5.6 | Pemasangan Liquid Drum | 0% | Not Yet | 2023-06-14 | 2023-08-04 | | 192 days | | |
1.5.6.1 | Pekerjaan Persiapan | 0% | Not Yet | 2023-06-14 | 2023-06-16 | | 241 days | | |
1.5.6.2 | Pekerjaan Penbesian Pondasi | 0% | Not Yet | 2023-06-23 | 2023-06-28 | | 229 days | | |
1.5.6.3 | Pekerjaan Pengecoran Beton | 0% | Not Yet | 2023-07-04 | 2023-07-06 | | 221 days | | |
1.5.6.4 | Pekerjaan Pemasangan Liquid Drum | 0% | Not Yet | 2023-07-25 | 2023-07-28 | | 199 days | | |
1.5.6.5 | Interconnecting to Other System | 0% | Not Yet | 2023-07-31 | 2023-08-01 | | 195 days | | |
1.5.6.6 | Precommissioning Liquid Drum | 0% | Not Yet | 2023-08-02 | 2023-08-04 | | 192 days | | |
1.5.7 | Pemasangan Cable & Cable Tray | 0% | Not Yet | 2023-07-04 | 2023-09-07 | | 158 days | | |
1.5.7.1 | Pekerjaan Persiapan | 0% | Not Yet | 2023-07-04 | 2023-07-07 | | 220 days | | |
1.5.7.2 | Pekerjaan Pembesian Pipe Support | 0% | Not Yet | 2023-07-07 | 2023-07-13 | | 214 days | | |
1.5.7.3 | Pekerjaan Pengecoran Sleeper Pipe Support | 0% | Not Yet | 2023-07-13 | 2023-07-18 | | 209 days | | |
1.5.7.4 | Pekerjaan Fabrikasi Pipe Support | 0% | Not Yet | 2023-07-12 | 2023-07-19 | | 208 days | | |
1.5.7.5 | Pemasangan Pipe Support | 0% | Not Yet | 2023-07-19 | 2023-07-26 | | 201 days | | |
1.5.7.6 | Pemasangan Cable Tray | 0% | Not Yet | 2023-08-01 | 2023-08-18 | | 178 days | | |
1.5.7.7 | Pulling Cable Power & Control | 0% | Not Yet | 2023-08-21 | 2023-09-07 | | 158 days | | |
1.5.8 | Pekerjaan Piping | 0% | Not Yet | 2023-08-14 | 2023-11-08 | | 96 days | | |
1.5.8.1 | Process gas System | 0% | Not Yet | 2023-08-14 | 2023-08-25 | | 171 days | | |
1.5.8.2 | Fire Water System | 0% | Not Yet | 2023-08-28 | 2023-09-08 | | 157 days | | |
1.5.8.3 | Utility Water System | 0% | Not Yet | 2023-09-11 | 2023-09-22 | | 143 days | | |
1.5.8.4 | Drain System | 0% | Not Yet | 2023-09-25 | 2023-10-06 | | 129 days | | |
1.5.8.5 | Vent System | 0% | Not Yet | 2023-10-09 | 2023-10-20 | | 115 days | | |
1.5.8.6 | Install Valve | 0% | Not Yet | 2023-10-09 | 2023-10-27 | | 108 days | | |
1.5.8.7 | Install Shut Down Valve | 0% | Not Yet | 2023-10-23 | 2023-10-27 | | 108 days | | |
1.5.8.8 | Install Slam Shut Valve | 0% | Not Yet | 2023-10-30 | 2023-11-03 | | 101 days | | |
1.5.8.9 | Install Pressure Safety Valve | 0% | Not Yet | 2023-06-11 | 2023-11-08 | | 96 days | | |
1.5.8.10 | Pekerjaan Pipeline System | 0% | Not Yet | 2023-10-18 | 2023-11-02 | | 102 days | | |
1.5.9 | Pemasangan Outdoor System | 0% | Not Yet | 2023-09-18 | 2023-11-16 | | 88 days | | |
1.5.9.1 | Install Field Instrument | 0% | Not Yet | 2023-09-18 | 2023-10-05 | | 130 days | | |
1.5.9.2 | Pemasangan Outdoor Lighting | 0% | Not Yet | 2023-10-03 | 2023-10-20 | | 115 days | | |
1.5.9.3 | Pemasangan Outdoor CCTV | 0% | Not Yet | 2023-09-18 | 2023-10-05 | | 130 days | | |
1.5.9.4 | Pemasangan Grounding & Lightning System | 0% | Not Yet | 2023-10-09 | 2023-10-24 | | 111 days | | |
1.5.9.5 | Pemasangan Safety Sign | 0% | Not Yet | 2023-11-08 | 2023-11-16 | | 88 days | | |
1.5.10 | Road & Drainage | 0% | Not Yet | 2023-06-14 | 2023-07-10 | | 217 days | | |
1.5.10.1 | Pekerjaan Access Road | 0% | Not Yet | 2023-06-14 | 2023-07-03 | | 224 days | | |
1.5.10.2 | Pemasangan Drainage | 0% | Not Yet | 2023-06-21 | 2023-07-10 | | 217 days | | |
1.6 | Precommissioning & Commissioning | 0% | Not Yet | 2023-10-25 | 2023-11-30 | | 74 days | | |
1.6.1 | Precommisioning | 0% | Not Yet | 2023-10-25 | 2023-11-20 | | 84 days | | |
1.6.1.1 | Precommissioning Control Building | 0% | Not Yet | 2023-11-16 | 2023-11-20 | | 84 days | | |
1.6.1.2 | Precommissioning Mechanical | 0% | Not Yet | 2023-11-13 | 2023-11-13 | | 91 days | | |
1.6.1.3 | Precommissioning Outdoor System | 0% | Not Yet | 2023-10-25 | 2023-10-27 | | 108 days | | |
1.6.1.4 | Leak Test Piping | 0% | Not Yet | 2023-11-09 | 2023-11-17 | | 87 days | | |
1.6.2 | Commisioning | 0% | Not Yet | 2023-11-27 | 2023-11-30 | | 74 days | | |
1.6.2.1 | Commissioning | 0% | Not Yet | 2023-11-27 | 2023-11-29 | | 75 days | | |
1.6.2.2 | Handover | 0% | Not Yet | 2023-11-30 | 2023-11-30 | | 74 days | | |