Master Schedule

Master Schedule
CUT OFF : 03 October 2023

Master Schedule Data
WBS Task Name Prog % Status Baseline Actual Overdue Remarks Action
Start Finish Finish
1.1Milestone Project 100%Done2023-04-17 2023-11-30 2023-10-01 74 days
1.1.1Surat Perintah VO Offtake Station Batang 100%Done2023-04-17 2023-04-17 2023-10-01 -
1.1.2Perancangan Selesai 100%Done2023-06-15 2023-06-15 2023-10-01 -
1.1.3Pengadaan LLI Selesai 100%Done2023-10-16 2023-10-16 2023-10-01 -
1.1.4Mechanical Completion 100%Done2023-11-24 2023-11-24 2023-10-01 -
1.1.5Privisonal Hand Over 100%Done2023-11-30 2023-11-30 2023-10-01 -
1.2Pekerjaan Persiapan 0%Not Yet2023-04-18 2023-05-23 265 days
1.2.1Project Facilities 0%Not Yet2023-04-18 2023-05-15 273 days
1.2.2Survey & Investigation 0%Not Yet2023-04-26 2023-05-23 265 days
1.3Engineering 100%Done2023-05-05 2023-06-15 2023-10-01 242 days
1.3.1Basic Engineering Design 100%Done2023-05-05 2023-06-02 2023-10-01 -
1.3.2Detailed Engineering Design 100%Done2023-05-16 2023-06-15 2023-10-01 -
1.4Procurement 5%On Prog2023-05-25 2023-11-07 97 days
1.4.1Pengadaan Bahan 5%On Prog2023-05-25 2023-11-07 97 days
1.4.1.1Long Lead Items 40%On Prog2023-05-25 2023-10-16 119 days
1.4.1.1.1Shut Down Valve 60%On Prog2023-05-25 2023-10-16 119 days
1.4.1.1.2Slam Shut Valve 70%On Prog2023-05-25 2023-10-16 119 days
1.4.1.1.3Pressure Safety Valve 70%On Prog2023-05-25 2023-10-16 119 days
1.4.1.1.4Metering & Regulating System 0%Not Yet2023-05-25 2023-10-16 119 days
1.4.1.1.5Monolithic Insulation Joint 0%Not Yet2023-05-25 2023-07-06 221 days
1.4.1.2Process Safety 0%Not Yet2023-06-05 2023-11-07 97 days
1.4.1.2.1Fire Extinguisher 0%Not Yet2023-06-05 2023-07-12 215 days
1.4.1.2.2Fire Suppression System 0%Not Yet2023-06-14 2023-10-09 126 days
1.4.1.2.3F & G System 0%Not Yet2023-06-14 2023-10-09 126 days
1.4.1.2.4Safety Sign 0%Not Yet2023-07-13 2023-11-07 97 days
1.4.1.3Mechanical 0%Not Yet2023-06-12 2023-10-06 129 days
1.4.1.3.1Liquid Drum 0%Not Yet2023-06-12 2023-07-24 203 days
1.4.1.3.2Slug Catcher 0%Not Yet2023-06-12 2023-09-01 164 days
1.4.1.3.3Odorizer System 0%Not Yet2023-06-12 2023-10-06 129 days
1.4.1.3.4Utility Water Tank 0%Not Yet2023-06-12 2023-08-04 192 days
1.4.1.4Electrical 0%Not Yet2023-06-12 2023-10-05 130 days
1.4.1.4.1LV Distribution Panel 0%Not Yet2023-06-12 2023-09-29 136 days
1.4.1.4.2UPS & DC System 0%Not Yet2023-06-12 2023-10-05 130 days
1.4.1.4.3Lighting & Receptacle System 0%Not Yet2023-06-12 2023-10-02 133 days
1.4.1.4.4Grounding & Lightning System 0%Not Yet2023-06-12 2023-10-05 130 days
1.4.1.4.5CCTV System 0%Not Yet2023-06-12 2023-09-15 150 days
1.4.1.4.6Power Cables 0%Not Yet2023-06-12 2023-08-14 182 days
1.4.1.4.7Cable Tray 0%Not Yet2023-06-12 2023-07-31 196 days
1.4.1.4.8Bulk Materials 0%Not Yet2023-06-12 2023-07-31 196 days
1.4.1.5Instrumentation 0%Not Yet2023-06-12 2023-10-06 129 days
1.4.1.5.1Actuated Valve 0%Not Yet2023-06-12 2023-09-15 150 days
1.4.1.5.2PCS/RTU System 0%Not Yet2023-06-12 2023-10-06 129 days
1.4.1.5.3Instrument Cables 0%Not Yet2023-06-12 2023-08-14 182 days
1.4.1.5.4Cable Tray 0%Not Yet2023-06-12 2023-07-31 196 days
1.4.1.5.5Instrument Fittings 0%Not Yet2023-06-12 2023-07-31 196 days
1.4.1.5.6Field Instrument 0%Not Yet2023-06-12 2023-09-15 150 days
1.4.1.5.7Junction Box 0%Not Yet2023-06-12 2023-09-08 157 days
1.4.1.5.8Bulk Materials 0%Not Yet2023-06-12 2023-09-08 157 days
1.4.1.6Pipeline 0%Not Yet2023-06-12 2023-10-17 118 days
1.4.1.6.1Barred Tee 0%Not Yet2023-06-12 2023-10-17 118 days
1.4.1.6.2Pipeline Material 0%Not Yet2023-06-12 2023-10-17 118 days
1.4.1.6.3Manual Valve 0%Not Yet2023-06-12 2023-10-17 118 days
1.4.1.6.4Bulk Materials 0%Not Yet2023-06-12 2023-10-17 118 days
1.4.1.7Piping 0%Not Yet2023-06-12 2023-08-25 171 days
1.4.1.7.1Pipe Material 0%Not Yet2023-06-12 2023-08-11 185 days
1.4.1.7.2Specialty Items 0%Not Yet2023-06-12 2023-08-25 171 days
1.4.1.7.3Manual Valve 0%Not Yet2023-06-12 2023-08-25 171 days
1.4.1.7.4Bulk Material (Bot&nuts, Garket, Flange, Elbow, etc) 0%Not Yet2023-06-12 2023-08-04 192 days
1.4.1.8Civil 0%Not Yet2023-06-05 2023-10-11 124 days
1.4.1.8.1Beton 0%Not Yet2023-06-14 2023-07-03 224 days
1.4.1.8.2Besi Beton 0%Not Yet2023-06-05 2023-06-22 235 days
1.4.1.8.3Steel Structure 0%Not Yet2023-06-20 2023-08-08 188 days
1.4.1.8.4HVAC System 0%Not Yet2023-06-22 2023-09-19 146 days
1.4.1.8.5Miscellenous Items 0%Not Yet2023-07-04 2023-10-11 124 days
1.5Construction 5%On Prog2023-05-29 2023-11-24 80 days
1.5.1Site Preparation 50%On Prog2023-05-29 2023-06-13 244 days
1.5.1.1Pekerjaan Cut & Fill 50%On Prog2023-05-29 2023-05-31 257 days
1.5.1.2Pekerjaan Pemadatan Tanah 100%Done2023-06-01 2023-06-07 2023-10-01 -
1.5.1.3Pekerjaan Sand Cone Test 0%Not Yet2023-06-08 2023-06-13 244 days
1.5.2Pembangunan Control Building (inc. Water Tank) 0%Not Yet2023-06-14 2023-11-24 80 days
1.5.2.1Pekerjaan Persiapan 0%Not Yet2023-06-14 2023-06-22 235 days
1.5.2.2Pekerjaan Pembesian Pondasi 0%Not Yet2023-06-23 2023-07-03 224 days
1.5.2.3Pekerjaan Pengecoran Beton 0%Not Yet2023-07-04 2023-07-10 217 days
1.5.2.4Pekerjaan Struktur Atas 0%Not Yet2023-07-11 2023-08-08 188 days
1.5.2.5Pekerjaan Atap Bangunan 0%Not Yet2023-08-09 2023-08-28 168 days
1.5.2.6Pemasangan Fasilitas Bangunan Lainnya 0%Not Yet2023-08-29 2023-09-11 154 days
1.5.2.7Pemasangan PCS System 0%Not Yet2023-10-09 2023-10-13 122 days
1.5.2.8Pemasangan UPS System 0%Not Yet2023-10-06 2023-10-12 123 days
1.5.2.9Pemasangan HVAC System 0%Not Yet2023-10-13 2023-10-26 109 days
1.5.2.10Pemasangan Fire & Gas Detector 0%Not Yet2023-10-27 2023-11-07 97 days
1.5.2.11Pemasangan Fire Suppression System 0%Not Yet2023-11-03 2023-11-15 89 days
1.5.2.12Pemasangan Lighting & Receptacle 0%Not Yet2023-10-03 2023-10-18 117 days
1.5.2.13Pemasangan Lightning Protection 0%Not Yet2023-10-19 2023-10-31 104 days
1.5.2.14Pemasangan LV Panel 0%Not Yet2023-10-02 2023-10-06 129 days
1.5.2.15Precommissioning Control Building 0%Not Yet2023-11-16 2023-11-24 80 days
1.5.3Pemasangan Odorizer System 0%Not Yet2023-06-14 2023-10-20 115 days
1.5.3.1Pekerjaan Persiapan 0%Not Yet2023-06-14 2023-06-22 235 days
1.5.3.2Pekerjaan Pembesian Pondasi 0%Not Yet2023-06-23 2023-06-28 229 days
1.5.3.3Pekerjaan Pengecoran Beton 0%Not Yet2023-07-04 2023-07-06 221 days
1.5.3.4Pekerjaan Pemasangan Shelter 0%Not Yet2023-08-09 2023-08-15 181 days
1.5.3.5Pekerjaan Pemasangan Odorizer System 0%Not Yet2023-10-09 2023-10-13 122 days
1.5.3.6Interconnecting to Other System 0%Not Yet2023-10-16 2023-10-17 118 days
1.5.3.7Precommissioning Odorizer System 0%Not Yet2023-10-18 2023-10-20 115 days
1.5.4Pemasangan Metering & Regulating Station 0%Not Yet2023-06-14 2023-11-10 94 days
1.5.4.1Pekerjaan Persiapan 0%Not Yet2023-06-14 2023-06-22 235 days
1.5.4.2Pekerjaan Pembesian Pondasi 0%Not Yet2023-06-23 2023-06-28 229 days
1.5.4.3Pekerjaan Pengecoran Beton 0%Not Yet2023-07-04 2023-07-06 221 days
1.5.4.4Pekerjaan Pemasangan Shelter 0%Not Yet2023-08-16 2023-08-28 168 days
1.5.4.5Pekerjaan Pemasangan Metering & Regulating Station 0%Not Yet2023-10-17 2023-10-25 110 days
1.5.4.6Pemasangan Lighting System 0%Not Yet2023-10-03 2023-10-16 119 days
1.5.4.7Pemasangan Fire Detection System 0%Not Yet2023-10-17 2023-10-25 110 days
1.5.4.8Pemasangan CCTV 0%Not Yet2023-10-26 2023-11-03 101 days
1.5.4.9Interconnecting to Other System 0%Not Yet2023-11-06 2023-11-07 97 days
1.5.4.10Precommissioning Odorizer System 0%Not Yet2023-11-08 2023-11-10 94 days
1.5.5Pemasangan Sludge Catcher 0%Not Yet2023-06-14 2023-09-14 151 days
1.5.5.1Pekerjaan Persiapan 0%Not Yet2023-06-14 2023-06-16 241 days
1.5.5.2Pekerjaan Pembesian Pondasi 0%Not Yet2023-06-23 2023-06-28 229 days
1.5.5.3Pekerjaan Pengecoran Beton 0%Not Yet2023-07-04 2023-07-06 221 days
1.5.5.4Pekerjaan Pemasangan Sludge Catcher 0%Not Yet2023-09-04 2023-09-07 158 days
1.5.5.5Interconnecting to Other System 0%Not Yet2023-09-08 2023-09-11 154 days
1.5.5.6Precommissioning Sludge Catcher 0%Not Yet2023-09-12 2023-09-14 151 days
1.5.6Pemasangan Liquid Drum 0%Not Yet2023-06-14 2023-08-04 192 days
1.5.6.1Pekerjaan Persiapan 0%Not Yet2023-06-14 2023-06-16 241 days
1.5.6.2Pekerjaan Penbesian Pondasi 0%Not Yet2023-06-23 2023-06-28 229 days
1.5.6.3Pekerjaan Pengecoran Beton 0%Not Yet2023-07-04 2023-07-06 221 days
1.5.6.4Pekerjaan Pemasangan Liquid Drum 0%Not Yet2023-07-25 2023-07-28 199 days
1.5.6.5Interconnecting to Other System 0%Not Yet2023-07-31 2023-08-01 195 days
1.5.6.6Precommissioning Liquid Drum 0%Not Yet2023-08-02 2023-08-04 192 days
1.5.7Pemasangan Cable & Cable Tray 0%Not Yet2023-07-04 2023-09-07 158 days
1.5.7.1Pekerjaan Persiapan 0%Not Yet2023-07-04 2023-07-07 220 days
1.5.7.2Pekerjaan Pembesian Pipe Support 0%Not Yet2023-07-07 2023-07-13 214 days
1.5.7.3Pekerjaan Pengecoran Sleeper Pipe Support 0%Not Yet2023-07-13 2023-07-18 209 days
1.5.7.4Pekerjaan Fabrikasi Pipe Support 0%Not Yet2023-07-12 2023-07-19 208 days
1.5.7.5Pemasangan Pipe Support 0%Not Yet2023-07-19 2023-07-26 201 days
1.5.7.6Pemasangan Cable Tray 0%Not Yet2023-08-01 2023-08-18 178 days
1.5.7.7Pulling Cable Power & Control 0%Not Yet2023-08-21 2023-09-07 158 days
1.5.8Pekerjaan Piping 0%Not Yet2023-08-14 2023-11-08 96 days
1.5.8.1Process gas System 0%Not Yet2023-08-14 2023-08-25 171 days
1.5.8.2Fire Water System 0%Not Yet2023-08-28 2023-09-08 157 days
1.5.8.3Utility Water System 0%Not Yet2023-09-11 2023-09-22 143 days
1.5.8.4Drain System 0%Not Yet2023-09-25 2023-10-06 129 days
1.5.8.5Vent System 0%Not Yet2023-10-09 2023-10-20 115 days
1.5.8.6Install Valve 0%Not Yet2023-10-09 2023-10-27 108 days
1.5.8.7Install Shut Down Valve 0%Not Yet2023-10-23 2023-10-27 108 days
1.5.8.8Install Slam Shut Valve 0%Not Yet2023-10-30 2023-11-03 101 days
1.5.8.9Install Pressure Safety Valve 0%Not Yet2023-06-11 2023-11-08 96 days
1.5.8.10Pekerjaan Pipeline System 0%Not Yet2023-10-18 2023-11-02 102 days
1.5.9Pemasangan Outdoor System 0%Not Yet2023-09-18 2023-11-16 88 days
1.5.9.1Install Field Instrument 0%Not Yet2023-09-18 2023-10-05 130 days
1.5.9.2Pemasangan Outdoor Lighting 0%Not Yet2023-10-03 2023-10-20 115 days
1.5.9.3Pemasangan Outdoor CCTV 0%Not Yet2023-09-18 2023-10-05 130 days
1.5.9.4Pemasangan Grounding & Lightning System 0%Not Yet2023-10-09 2023-10-24 111 days
1.5.9.5Pemasangan Safety Sign 0%Not Yet2023-11-08 2023-11-16 88 days
1.5.10Road & Drainage 0%Not Yet2023-06-14 2023-07-10 217 days
1.5.10.1Pekerjaan Access Road 0%Not Yet2023-06-14 2023-07-03 224 days
1.5.10.2Pemasangan Drainage 0%Not Yet2023-06-21 2023-07-10 217 days
1.6Precommissioning & Commissioning 0%Not Yet2023-10-25 2023-11-30 74 days
1.6.1Precommisioning 0%Not Yet2023-10-25 2023-11-20 84 days
1.6.1.1Precommissioning Control Building 0%Not Yet2023-11-16 2023-11-20 84 days
1.6.1.2Precommissioning Mechanical 0%Not Yet2023-11-13 2023-11-13 91 days
1.6.1.3Precommissioning Outdoor System 0%Not Yet2023-10-25 2023-10-27 108 days
1.6.1.4Leak Test Piping 0%Not Yet2023-11-09 2023-11-17 87 days
1.6.2Commisioning 0%Not Yet2023-11-27 2023-11-30 74 days
1.6.2.1Commissioning 0%Not Yet2023-11-27 2023-11-29 75 days
1.6.2.2Handover 0%Not Yet2023-11-30 2023-11-30 74 days
Description
Status Done
Status On Going
Status Not Yet
Status On Going & Overdue Date
Status Not Yet & Overdue Date